In short
- The Act covers work to a shared wall, new walls on the boundary, and some digging near a neighbour’s foundations.
- Notice is two months before work to a party wall, one month for boundary walls and excavations.
- Your neighbour has 14 days to consent. If they don’t reply, or they dissent, a dispute is deemed to have arisen and surveyors draw up an award.
- The Act is separate from planning and building regulations. Building control does not administer it.
Which works need a party wall notice?
The Act covers three kinds of work: work to an existing party wall, new walls at the boundary, and excavation near a neighbour’s building. GOV.UK’s examples include:
- Cutting into a party wall, for example to take the end of a steel beam.
- Removing chimney breasts from a party wall.
- Making a party wall taller, shorter or deeper, or underpinning it.
- Knocking down and rebuilding a party wall.
- Building a new wall on or at the boundary line.
- Digging within three metres of a neighbour’s building and below its foundations, or within six metres where the dig would cut a 45-degree line down from them.
How much notice do you have to give?
At least two months before work to a party wall or party structure starts. At least one month before building a new wall on the boundary, and one month before excavating near a neighbour’s foundations. The notice describes the work and the planned start date.
A notice lapses if the work hasn’t started within a year, so don’t serve it too early. Notices can be sent by email if both owners have agreed to that.
Consent or dispute
Your neighbour, the adjoining owner, has 14 days to respond in writing. If they consent in writing, the work can go ahead as described in the notice. It still makes sense to record the condition of their side before you start, so any later claim can be checked.
If they dissent, or don’t reply within 14 days to a party wall or excavation notice, the Act treats it as a dispute. That sounds worse than it is. It simply means surveyors are appointed to settle the terms.
Party wall surveyors and the award
The two owners can agree on one surveyor to act for both, or each appoint their own. If two surveyors can’t agree a point, they select a third. Neither owner can act as their own surveyor.
The surveyors produce a party wall award. It sets out the work to be done, when and how it will be carried out, how the neighbour’s property is protected, and access for the surveyors to inspect. It often includes a schedule of the condition of the neighbour’s property. Usually the owner doing the work pays the surveyors’ costs.
The award is binding. Either owner can appeal to the county court within 14 days of it being served.
How we handle it
We arrange party wall agreements as part of our structural engineer and building control service, so the notice goes out in good time and the work isn’t held up. Where your neighbour wants their own surveyor, that is their right under the Act, and we work with them.
This is general guidance, not legal advice. For an unusual case, the GOV.UK explanatory booklet and a party wall surveyor are the places to start.
