It is one of the most common faults found in older London houses. A previous owner took out the breasts, and the brickwork above was left resting on whatever was nearby.

A Victorian London terrace in yellow and red brick with bay windows and chimney stacks topped with rows of clay pots

In short

  • If the breast below is gone, the chimney above must sit on steel or approved brackets. If it doesn’t, it needs attention.
  • Look in the loft: brickwork resting on timber joists, cracks, or a stack that leans are warning signs.
  • The fix is to prop it, then install support designed by a structural engineer and inspected by building control.
  • Work done without approval since November 1985 can be regularised by the council, which helps when you sell.

How to tell if a removed chimney breast is unsupported

Start in the rooms. If a chimney breast has gone from the ground floor but the one in the bedroom above is still there, something has to be carrying it. The same applies to the loft section and stack when breasts below have been removed.

Then look in the loft with a torch. You are looking for what the chimney is sitting on.

  • Brickwork resting directly on ceiling joists, timber offcuts or a loose board.
  • No steel beam and no steel brackets under the remaining brickwork.
  • Cracks in the chimney brickwork or the party wall near it.
  • Crumbling or missing bricks at the base of the loft section.
  • Ceilings that have dropped or cracked below the chimney, or a stack that leans when seen from the street.

Why it matters

A chimney stack and loft breast weigh a great deal. Timber joists were not designed to carry that load, and the brickwork can move or drop over time. In a storm, or when the timber weakens, the risk to the people below is real.

It can also affect your neighbour. The chimney may share brickwork and flues with theirs, so movement on your side can damage their side too.

Getting it made safe

If there is any sign of movement, the first step is temporary support: steel props to take the weight off the joists. A structural engineer then designs permanent support, usually steel beams bearing on padstones in the walls, or decides that removing the stack is the better answer.

The permanent work goes through building control in the same way as a new removal, with inspections as it is done. Six of our 34 Which? reviews are from customers whose chimney had been left unsupported or botched by someone else. We put that work right and get it certified.

Regularising old work so it is on record

If the original removal was done without building regulations approval, your council can issue a regularisation certificate. It applies to unauthorised work carried out on or after 11 November 1985, and only the local authority can do it, not a private approver.

The council may ask for parts of the work to be opened up for inspection, and may list work needed before it will issue a certificate. Where new support is going in, ask your council’s building control whether they want a regularisation application, a new application for the remedial work, or both.

Selling or buying a house with an unsupported chimney

Buyers’ surveyors often spot a missing breast and look for the support in the loft. Their solicitor will ask for the building regulations completion certificate. Without approval, GOV.UK warns you may not have the certificates you need when you sell.

Sellers are sometimes offered indemnity insurance instead. That deals with the legal risk of the council taking action, not with the chimney itself, so it does nothing about the load in the loft. If you are buying, have it looked at before you exchange.

Questions

How do I know if my chimney breast removal was done properly?

Look in the loft for steel beams or approved steel brackets under the remaining brickwork, and ask for the building control completion certificate. If there is neither, have it checked.

Can I get building regulations sign-off for a chimney removed years ago?

For work done on or after 11 November 1985 you can apply to your council for a regularisation certificate. They may need parts opened up and may ask for remedial work first.

Get a quote

Describe the project and where it is. We’ll reply to arrange a visit, then send an itemised written quote.

  1. We reply within 2 working days
  2. We visit and look at the project properly
  3. You get an itemised, provisional quotation

Rather talk it through? Call or WhatsApp Lee on 07875 545032.

Photos help. Send them from the contact page or reply to our email with them.

What’s it about?

We reply to every enquiry within 2 working days. Your details are only used to reply about this project.

Enquiry sent

Thanks, that’s with LR Building

We reply to every enquiry within two working days.

Not heard back by then? Call or WhatsApp Lee on